Phase 3 ends and phase 4 begins. The water main replacement project is now in its fourth installment.

Craig Hemingway is the Communications Manager with the city of Moose Jaw, he detailed more about what's being done.

"It's primarily surface work like concrete and final paving of the locations. There is a little bit of service work and connection work as well but the bulk of it pertains to surface work and paving."

Craig also explained how long this phase is expected to take.

"It should be about three to four weeks in those locations so early June it should be wrapped up."

More details on phase 5 of the project will be released soon.