Spring has arrived and with it brings construction and road maintenance season.
Below is the daily road report from May 3:
WELLESLEY ST. – Grandview St W. to 1st Ave SE
Detour – Use 1st Ave. SE to Access/Exit Wellesley Park Area
Sanitary Forcemain Installation
April 18th – 22nd, 2022
SASKATCHEWAN ST E - MAIN ST N TO 1st AVE NE
Main St N and 1st Ave NE intersections will remain open at this time.
Beginning April 25th, 2022.
Water main replacement
GRANDVIEW ST W - 6TH AVE SW TO 8TH AVE SW
6th Ave NW and 8th Ave NW intersections will remain open at this time.
Beginning April 25th, 2022
Water main replacement
9TH AVE. NE – STADACONA ST. E TO FAIRFORD ST. E
Sanitary Sewer Dig Repairs
Planned: April 26th – 29th, 2022
Ongoing
1000 BROWN ST – 10th Ave NW to 11th Ave NW
Sewer & water relay
Ongoing
1000 HENRY ST - 10th Ave NW to 11th Ave NW
Sewer & water relay
Ongoing
1000 BLK ATHABASCA ST E - 10th Ave NW to 11th Ave NW
Water Main Break
Ongoing